The thesis describes Linear Scheduling Method used for linear projects, method is presented using Microsoft Excel and Tilos. Tunnel T2 from project Drugi tir Divača – Koper is taken as a real case study. The existing schedule, which was produced in Excel, is analysed, and the schedule produced in Tilos is presented in addition. As the tunnels in Slovenia are being made according to the so-called New Austrian Tunneling Method, its procedures are described in this paper, as well as tendering and costing procedures at contract drafting, as unpredictability in geology causeses diffrences between common contract practices and contracts in tunnel engineering.
|