Subject of this diploma thesis is presentation of pavement execution in length of 1200m through Jagnjenica settlement, together with sewer infrastructure alignment and scheduling, made specifically for this project.
I conducted an analysis of contractual schedule and based on chosen literature, using Microsoft Project computer program, I made a correction of schedule to the point, that it's useful for project monitoring.
From construction journals, I summed up the actual data about execution of this project and entered those data into schedule. Based on this I was able to get an insight to actual state of construction course. I presented my findings in the last part of the thesis.
|