Pretočni čas izdelave transporterja
ID Koren, Davorin (Author), ID Kušar, Janez (Mentor) More about this mentor... This link opens in a new window

.pdfPDF - Presentation file, Download (2,84 MB)
MD5: E0017E401E2B9E737CCCF9C1C95ABFCC
.pdfPDF - Appendix, Download (194,05 KB)
MD5: E997F3EE0C6421FDC24E67CA1D966661
.pdfPDF - Appendix, Download (379,29 KB)
MD5: 843977DD6FE66409A4F0D133C62EFF45

Abstract
Diplomsko delo obravnava določanje pretočnega časa izdelave transporterja. V teoretičnem delu so predstavljene družine transporterjev, ki imajo podoben način izvedbe proizvodnega procesa. Ker podjetje želi naročilo transporterja obravnavati kot projekt, je potrebno za posamezno družino transporterjev izdelati standardno strukturo projekta, s katero se lahko na osnovi poznavanja pretočnih časov aktivnosti ter tehnoloških operacij, za vsako naročilo določi pretočni čas izvedbe naročila in s tem čas trajanja projekta. Projekt izdelave transporterja vsebuje vse aktivnosti od povpraševanja kupca, nabave materiala, izvedbe tehnoloških in montažnih operacij ter končnega testa naprave in opreme. V zadnjem delu je prikazan primer uporabe standardne strukture projekta na primeru konkretnega naročila.

Language:Slovenian
Keywords:pretočni časi, projekti, projektno vodenje, mrežni diagrami, terminski plani, analiza obremenitve virov
Work type:Bachelor thesis/paper
Typology:2.11 - Undergraduate Thesis
Organization:FS - Faculty of Mechanical Engineering
Place of publishing:Ljubljana
Publisher:[D. Koren]
Year:2019
Number of pages:XX, 62 str.
PID:20.500.12556/RUL-106195 This link opens in a new window
UDC:658.51:621.867(043.2)
COBISS.SI-ID:16485659 This link opens in a new window
Publication date in RUL:08.02.2019
Views:2157
Downloads:603
Metadata:XML DC-XML DC-RDF
:
Copy citation
Share:Bookmark and Share

Secondary language

Language:English
Title:Manufacturing flow time of conveying systems
Abstract:
The graduation thesis deals with determining flow time of a conveyor production. In the theoretical part, conveyor families that have a similar way of production process implementation are presented. As the company wants to treat order of a conveyor as a project, a standard project structure shall be prepared for individual conveyor family, based on which, as well as based on knowledge of flow times of activities and technological operations, flow time of order implementation can be determined, therefore also project duration. The project of the conveyor production consists of all activities: customer’s demand, material purchase, implementation of technological and installation operations, as well as final machine and equipment test. In the last part of the thesis, an example of use of a standard project structure on the basis of an actual order is presented.

Keywords:flow time, projects, project management, network diagrams, resource load analysis