izpis_h1_title_alt

Nov koncept napajanja lastne porabe RTP Beričevo
ID MIHELIČ, JANEZ (Author), ID Mihalič, Rafael (Mentor) More about this mentor... This link opens in a new window

.pdfPDF - Presentation file, Download (2,62 MB)
MD5: 93A7E2CF1F74E6537F1EB3CB65C87028
PID: 20.500.12556/rul/b2265946-39d3-45f7-b58e-f524ea5c0b0f

Abstract
Vir lastne porabe RTP Beričevo mora bit zanesljiv, ker gre za objekt posebnega pomena za celotno Slovenijo. Družba ELES je v preteklosti imela težavo z okvaro enega od transformatorjev na terciarnem navitju, zato se je preventivno odločila za prenovo oziroma dogradijo lastne porabe s transformacijo 110/20 kV. Izbirali so med tremi možnostmi. Prva možnost je bila, da se v primeru okvare transformator obnovi, in da se izvodi terciarnega navitja bolj izolirajo oziroma zaščitijo. Ta možnost ni ekonomična in ogroža zanesljivost prenosa EE. Druga možnost je bila napajanje lastne porabe preko distribucijskega omrežja. Zaradi nezanesljivosti takega napajanja se je družba ELES odločila za tretjo možnost ‒ preventivno izgradnjo nove lastne porabe. Ta možnost finančno ni najbolj ugodna, vendar sta pretehtali zanesljivost in neodvisnost napajanja lastne porabe od drugih virov napajanja, ki niso v lasti ali pod nadzorom družbe ELES.

Language:Slovenian
Keywords:lastna poraba, RTP Beričevo, distribucijsko omrežje, terciarno navitje
Work type:Undergraduate thesis
Organization:FE - Faculty of Electrical Engineering
Year:2015
PID:20.500.12556/RUL-72379 This link opens in a new window
Publication date in RUL:15.09.2015
Views:9466
Downloads:905
Metadata:XML RDF-CHPDL DC-XML DC-RDF
:
Copy citation
Share:Bookmark and Share

Secondary language

Language:English
Title:New auxiliary power supply in Beričevo station
Abstract:
The supply system of distribution transformer station Beričevo has to be reliable, because it is an important facility in Slovenia. ELES Ltd. has had problems in the past with the failure of one of the transformers at the tertiary winding, hence they have decided for renovation and built a 110/20 kV transformation into the supply system. They chose among three options. The first option was to reconstruct the transformer in the event of failure and to insulate and protect the tertiary winding’s leads. This option is not economical and undermines the reliability of electric power transmission. The second option was to power the supply system through a distribution network. Because of the unreliability of such power, the ELES Ltd. decided on the third option – the construction of a new supply system. This option is not the most financially favourable, but they‘ve assessed the reliability and independence of powering the supply system from other power sources that are not owned or controlled by ELES Ltd.

Keywords:supply system, distribution transformer station Beričevo, distribution network, tertiary winding