Izdelava terminskega plana izgradnje tunela na osnovi tehnike linearnega planiranja : diplomska naloga št.: 462/B-GR
ID Kump, Gaj (Author), ID Čas, Bojan (Mentor) More about this mentor... This link opens in a new window, ID Srdič, Aleksander (Comentor)

.pdfPDF - Presentation file, Download (3,92 MB)
MD5: E1BB57758ACD1CED3FB2537DB6B2A987

Abstract
V diplomski nalogi je opisana metoda linearnega planiranja pri linijskih projektih, metoda je predstavljena tudi z uporabo programskih orodji Microsoft Excel in Tilos. Kot primer projekta je obravnavan realen primer predora T2, ki bo izveden v sklopu projekta Drugi tir Divača – Koper. Analiziran je obstoječi terminski plan, ki je bil izdelan v programskem okolju Excel, dodatno pa je predstavljen tudi terminski plan, ki smo ga izdelali v s programskim paketom Tilos. Ker se predore pri nas izvaja po t.i. Novi avstrijski metodi, so predstavljeni njeni postopki in posebnosti. Predstavljene so tudi posebnosti pri sestavi pogodbe med naročnikom in izvajalcem ter njena določila, ki se zaradi nepredvidljivosti geologije pri izkopu, oblikujejo drugače kot pri večini ostalih pogodb.

Language:Slovenian
Keywords:gradbeništvo, diplomske naloge, UNI, GR, B-GR, predorogradnja, NATM, linearno planiranje, Tilos, prilagodljiva gradbena pogodba, časovne norme
Work type:Bachelor thesis/paper
Typology:2.11 - Undergraduate Thesis
Organization:FGG - Faculty of Civil and Geodetic Engineering
Place of publishing:Ljubljana
Publisher:[G. Kump]
Year:2023
Number of pages:VIII, 27 str., 4 f. zganj. pril
PID:20.500.12556/RUL-151148-f6fde56d-c92c-035f-2f2f-1071948d5b8a This link opens in a new window
UDC:624.19:658.513.3/.4(043.2)
COBISS.SI-ID:178361859 This link opens in a new window
Publication date in RUL:30.09.2023
Views:1197
Downloads:75
Metadata:XML DC-XML DC-RDF
:
Copy citation
Share:Bookmark and Share

Secondary language

Language:English
Title:Developing a timetable for the construction of the tunnel based on the Linear Scheduling Method : graduation thesis no.: 462/B-GR
Abstract:
The thesis describes Linear Scheduling Method used for linear projects, method is presented using Microsoft Excel and Tilos. Tunnel T2 from project Drugi tir Divača – Koper is taken as a real case study. The existing schedule, which was produced in Excel, is analysed, and the schedule produced in Tilos is presented in addition. As the tunnels in Slovenia are being made according to the so-called New Austrian Tunneling Method, its procedures are described in this paper, as well as tendering and costing procedures at contract drafting, as unpredictability in geology causeses diffrences between common contract practices and contracts in tunnel engineering.

Keywords:graduation thesis, civil engineering, tunneling, NATM, linear project planning, Tilos, flexible construction contract