izpis_h1_title_alt

Časovna analiza poteka sanacije OŠ Trnovo : diplomska naloga št.: 420/B-GR
ID Zemljič, Urban (Author), ID Srdič, Aleksander (Mentor) More about this mentor... This link opens in a new window, ID Kušar, Matej (Co-mentor)

.pdfPDF - Presentation file, Download (5,11 MB)
MD5: 4F212349587E2FFEBED451547FB247CC

Abstract
V diplomskem delu je obravnavana OŠ Trnovo, ki je bila med letom 2021 in 2022 energetsko in statično obnovljena oz. ojačana. Predstavljen je objekt ter podroben opis predvidenih in dejansko izvedenih del. Prikazan je tudi terminski plan pred začetkom gradnje ter med potekom gradnje oz. sanacije. Narejena je tudi analiza časovnih odstopanj v programu Microsoft Project, ki prikazuje oziroma primerja načrtovani potek del z dejanskim potekom del. V analizi so zajeta tudi nepredvidena dela in vpliv le teh na končni rok izvedbe.

Language:Slovenian
Keywords:gradbeništvo, diplomska naloga, UNI, GR, terminski plan projekta, Microsoft Project, časovna analiza odstopanj
Work type:Bachelor thesis/paper
Typology:2.11 - Undergraduate Thesis
Organization:FGG - Faculty of Civil and Geodetic Engineering
Place of publishing:Ljubljana
Publisher:[U. Zemljič]
Year:2022
Number of pages:VII, 34 str., 2 pril.
PID:20.500.12556/RUL-141371-4a248145-9319-3dec-725c-9ee2f02fad68 This link opens in a new window
UDC:69.05:727(497.4)(043.2)
COBISS.SI-ID:139452675 This link opens in a new window
Publication date in RUL:29.09.2022
Views:614
Downloads:93
Metadata:XML RDF-CHPDL DC-XML DC-RDF
:
Copy citation
Share:Bookmark and Share

Secondary language

Language:English
Title:Schedule analysis of Trnovo primary school renovation project : graduation thesis no.: 420/B-GR
Abstract:
This diploma thesis deals with project of Trnovo primary school renovation. The school building was upgraded from the point of energetic efficiency and static reinforcement. This thesis includes the presentation of the structure itself and the works, which were made to improve the quality of the building. It shows not only the initial term plan but also how it was changed during the construction. Schedule delay analysis was made using Microsoft Project. As a result, we can see which circumstances and work execution conditions has the major impact on delays that occurred. Also, the analysis includes unexpected works and their effect on the project completion.

Keywords:graduation thesis, civil engineering, project schedule, Microsoft Project, delay analysis

Similar documents

Similar works from RUL:
Similar works from other Slovenian collections:

Back