Analiza poteka izvedbe del projekta rekonstrukcije cestnega odseka : diplomska naloga
ID Žižmond, Luka (Author), ID Srdič, Aleksander (Mentor) More about this mentor... This link opens in a new window

.pdfPDF - Presentation file, Download (3,34 MB)
MD5: 1974446C850C90DEC4D934E26691743C
.pdfPDF - Appendix, Download (792,54 KB)
MD5: 94D3CB8452090D116E209FB591089BA6

Abstract
Vsak gradbeni projekt je unikaten. Pri vsakem projektu sodelujejo številni udeleženci, ki med seboj usklajujejo bolj ali manj povezane dejavnosti. Rezultat in uspeh projekta sta v veliki meri odvisna od dobrega in uspešnega sodelovanja vseh akterjev, čar poteka pa je v tem, da se projekt nikoli ne ponovi pod enakimi pogoji. Za kvalitetno izvedbo projekta in predvsem izvedbo v roku so potrebni dobra priprava, usklajevanje ter ustrezno usposobljeni ljudje. Zaradi velike možnosti pojava nepredvidenih dogodkov je treba pred začetkom izvedbe imeti dobro in skrbno pripravljen plan dela, saj lahko le tako hitro in uspešno rešujemo nastale situacije. V diplomskem delu je najprej predstavljen projekt, pri katerem sem sodeloval tudi sam. Gre za rekonstrukcijo dela ceste, katere namena sta izboljšanje protipoplavne varnosti ter ureditev novih komunalnih vodov. Na podlagi pridobljenega gradiva % gradbenega dnevnika, pogodbenega predračuna, knjige obračunskih izmer in terminskega plana % sem natančno predstavil ključne podrobnosti projekta. V nadaljevanju sem naredil analizo s stroškovnega ter časovnega vidika. Za potrebe stroškovne analize sem v programu Excel primerjal vrednosti pogodbenega predračuna s končnim obračunom ter prikazal in opisal vsa odstopanja. Za potrebe časovne analize sem v programu Microsoft Project primerjal prvotno izdelan plan, rebalans plana ter dejanski potek del. Nastale zamike in zamude tekom gradnje sem opisal in obrazložil v stroškovni analizi, kjer so utemeljeni vzroki nastanka le-teh.

Language:Slovenian
Keywords:gradbeništvo, diplomska naloga, VSŠ, GR, GR-OG, analiza poteka izvedbe del, rekonstrukcija cestnega odseka, pritisk svežega betona, stroškovna in časovna analiza, terminski plan
Work type:Bachelor thesis/paper
Typology:2.11 - Undergraduate Thesis
Organization:FGG - Faculty of Civil and Geodetic Engineering
Place of publishing:Ljubljana
Publisher:[L. Žižmond]
Year:2020
Number of pages:IX, 60 str.
PID:20.500.12556/RUL-120596 This link opens in a new window
UDC:658.5:69(043.2)
COBISS.SI-ID:43668227 This link opens in a new window
Publication date in RUL:23.09.2020
Views:1932
Downloads:232
Metadata:XML DC-XML DC-RDF
:
Copy citation
Share:Bookmark and Share

Secondary language

Language:English
Title:The analysis of the implementation of works on the road section reconstruction project : graduation thesis
Abstract:
Every construction project is unique. Each project involves many participants who coordinate more or less related activities. The result and success of the project largely depend on the great and successful cooperation of all actors, and the charm lies in the fact that the project is never repeated under the same conditions. Good preparation, coordination and suitably qualified people are needed for the quality implementation of the project and especially the implementation within the deadline. Due to the high possibility of unforeseen events, it is necessary to have a well-prepared work plan before the start of the implementation, as this is the only way to resolve the situations that arise quickly and successfully. The diploma work first presents a project that I took part in as well. It is a reconstruction of a part of a road, the purpose of which is to improve flood safety and to arrange new municipal lines. On the basis of the obtained material - construction diary, contract estimate, book of accounting measurements and time plan % I presented the key details of the project in detail. In the following, I made an analysis from a cost and timeframe point of view. For the purposes of cost analysis, I compared the values of the contractual estimate with the final statement in Excel and showed and described all the deviations. For the purposes of time analysis, I compared the originally prepared plan, the rebalance of the plan and the actual course of work in the Microsoft Project program. The resulting delays and delays during construction have been described and explained in the cost analysis, where the causes of these are justified.

Keywords:graduation thesis, civil engineering, analysis of the progress of works, reconstruction of the road section, costal and time analysis, project schedule