The development has made cable cranes more mobile, their moving is frequent and relocation time represents a great part of total time. The purpose of my thesis is to learn, what influence the conditions of terrain, line characteristics and organisation of work have on setting up and setting down time. 203 Syncrofalke cable crane lines have been analysed on the territory ofSlovenia. The analysis has been carried out by the help of pivot table in Excel programme and statistical tests in SPSS programme. The time of setting down is aproximately half shorter then the time of setting up. The time of setting up is lengthened by the lengthening of line. The probability of setting up intermediate supports is also increased which considerably lengthenthe time of setting up. The times are longer with the down skidding than with the up skidding which as well increases the relocation time with theparalel lines compared with the fan-shaped lines. By the increase of wood concentration the time of setting up shortens up to concentration 1,25 m3/m. With greater concentrations there is not enough data for an accurate estimation. The time of setting up and setting down is also influenced by organisation of work. The shortest is in the group of 2 workers. All the factors which influence relocation time act together, that is why the influence of an individual is difficult to find out.
|