Metodologija za finančno analizo in kontrolo izvajanja projektov v gradbeništvu : magistrsko delo
ID Kuhar, Zoran (Author), ID Šelih, Jana (Mentor) More about this mentor... This link opens in a new window

.pdfPDF - Presentation file, Download (1,89 MB)
MD5: F36B5BED3DF35BF1B4A5565D1660692B
PID: 20.500.12556/rul/f92d54a1-cf20-443c-8c73-2c524d2e106b

Abstract
Zaradi vse večje potrebe po učinkovitem spremljanju stroškov na projektu, izvirajoče iz teţko predvidljivega poteka gradnje, pogostih investitorjevih prekinitev del, zaradi slabo definiranih potreb v fazi projektiranja, negotovosti prodaje in trenutne krize v gradbeništvu, bomo v magistrski nalogi prikazali metodologijo za finančno analizo in kontrolo pri izvajanju gradbenih projektov. Metodologija, ki smo jo razvili, temelji na tehniki analize prisluţene vrednosti (EVA) in metodi neto sedanje vrednosti (NPV). Z njuno zdruţitvijo smo dobili posodobljeno metodologijo, ki upošteva vrednost denarja skozi čas in smo jo zato poimenovali neto sedanja prisluţena vrednost (NSPV). S pomočjo NSPV je moţno spremljati projektne stroške na podlagi primerjave osnovnega denarnega toka, ki ga diskontiramo na začetni termin, torej na začetek projekta. S tem vključimo časovno komponento, tako da so zneski prihodkov in odhodkov v različnih časih primerljivi. V magistrskem delu bomo torej predstavili metodologijo, ki bo vodjem projektov pomagala zmanjševati tveganja na projektu, pomagala obvladovati stroške in bo hkrati tudi razmeroma preprosta za uporabo, koristiti pa jo bo mogoče v celotnem ţivljenjskem ciklu gradbenega projekta.

Language:Slovenian
Keywords:gradbeništvo, magistrska dela, gradnja, metodologija prislužene vrednosti, neto sedanja vrednost, neto sedanja prislužena vrednost, denarni tokovi, obvladovanje tveganja, vodenje projektov
Work type:Master's thesis
Typology:2.09 - Master's Thesis
Organization:FGG - Faculty of Civil and Geodetic Engineering
Place of publishing:Ljubljana
Publisher:[Z. Kuhar]
Year:2011
Number of pages:XV, 102 str., [4] str. pril.
PID:20.500.12556/RUL-32552 This link opens in a new window
UDC:624:35.073.52(043.3)
COBISS.SI-ID:5582433 This link opens in a new window
Publication date in RUL:10.07.2015
Views:2555
Downloads:615
Metadata:XML RDF-CHPDL DC-XML DC-RDF
:
Copy citation
Share:Bookmark and Share

Secondary language

Language:English
Title:Methodology for financial analysis and controlling construction projects
Abstract:
The increasing need for efficient monitoring of project costs that derives from poorly predictable construction execution, frequent interruptions of work from the client’s side, poorly defined needs in the design phase, the uncertainty of sales and the current crisis in the construction industry dictates the development of methodology for financial analysis and control to be used during construction project execution. The developed methodology is based on technique of earned value analysis (EVA) and net present value (NPV) method. By merging these two methods, a new, improved methodology, the so-called net present earned value (NPEV), that takes into consideration the value of money over time is obtained. By using NPEV, it is possible to monitor project costs by comparing the basic real discounted cash flow (discounted to the initial term, i.e. to the beginning of the project), to the planned cash flow. The new methodology therefore includes the time component, and enables the comparison of income and expenditure amounts at different times. The proposed methodology has the potential to reduce the project risks and helps to keep costs under control. Since it is relatively simple to use, it will facilitate the day-to-day work of a project manager throughout the life cycle of a construction project.

Keywords:civil engineering, master of science thesis, construction, earned value management, net present value, net present earned value, risk management, project management, MS Project, cash flows