izpis_h1_title_alt

Varovanje gradbene jame parkirno garažne hiše v Ljubljani : diplomska naloga
ID Hafner, Matej (Author), ID Pulko, Boštjan (Mentor) More about this mentor... This link opens in a new window, ID Logar, Janko (Comentor)

.pdfPDF - Presentation file, Download (22,43 MB)
MD5: E01666EA9D25E88184DBBCE80D91245A
PID: 20.500.12556/rul/9754a481-c7de-4c11-b2d1-0259071c6c38
.zipZIP - Appendix, Download (1,60 MB)
MD5: C8577289E89613802E1EA9460DFAD0ED
PID: 20.500.12556/rul/9b953184-a2ff-462c-b9d4-03594500cd6b

Abstract
V diplomski nalogi je obravnavano varovanje gradbene jame za objekt parkirno garažne hiše v Ljubljani. Varovalna konstrukcija je bila izvedena s sidranimi slopi po tehnologiji injektiranja pod visokimi pritiski (jet grouting). Sidranje smo izvedli z začasnimi geotehničnimi sidri v enem ali dveh nivojih. V nalogi je podan pregled postopkov za izvedbo jet grouting slopov in začasnih geotehničnih sider po veljavnih standardih. Pozornost je posvečena načinom izvedbe, ki so uveljavljeni pri nas, in problemom, ki se pojavljajo zaradi odstopanja od zhatev tehnične regulative ali nezmožnosti upoštevanja le-te. To je delno posledica zastarele opreme in utečenih postopkov izvajanja del. Dodatno pa na to vplivajo tudi zahteve po čim cenejši izvedbi gradbenih del. V nalogi so predstavljene izkušnje pridobljene med izvedbo varovalne konstrukcije gradbene jame, rezultati kontrolnih preiskav in problemi, ki so se pojavili med izvedbo del, ter rešitve teh problemov. V fazi izvedbe varovalne konstrukcije iz jet grouting slopov smo največ pozornosti posvetili tehnologiji enofaznega postopka injektiranja in njeni učinkovitosti v danih razmerah. Pri izvedbi geotehničnih sider pa smo največ pozornosti posvetili vgradnji in napenjanju preskusnih sider. Na gradbišču nastali problemi so lahko tudi posledica nepopolne gradbene dokumentacije, vključno s starimi in pomanjkljivimi načrti sosednjih objektov. V nalogi je prav tako obravnavano reševanje problemov, povezanih z nepričakovano sestavo temeljnih tal. Ta je pomembno vplivala na težave in zamude pri izvedbi in nemoteno napredovanje del.

Language:Slovenian
Keywords:gradbeništvo, diplomska naloga, VSŠ, gradbena jama, jet grouting, modificiran postopek jet grouting, injekcijska masa, začasna geotehnična sidra, sidrne vrtine, napenjanje sidra, preskusna sidra
Work type:Undergraduate thesis
Typology:2.11 - Undergraduate Thesis
Organization:FGG - Faculty of Civil and Geodetic Engineering
Place of publishing:Ljubljana
Publisher:[M. Hafner]
Year:2016
Number of pages:XII, 70 str., 8 pril.
PID:20.500.12556/RUL-81518 This link opens in a new window
COBISS.SI-ID:7452257 This link opens in a new window
Publication date in RUL:29.04.2016
Views:5109
Downloads:897
Metadata:XML DC-XML DC-RDF
:
Copy citation
Share:Bookmark and Share

Secondary language

Language:English
Title:Protection of construction pit for car-park building in Ljubljana
Abstract:
The subject of this thesis is the execution construction pit for multi-storey car-park building in Ljubljana. The supporting structure was made with high pressure grouting (e.q jet grouting), and anchored with temporary ground anchors in one or two levels. An overview of jet grouting and temporary ground anchors procedures accoding to current standards is shown. A special attention is put on the currently valid execution of works in our country. We primarily examined the problems occurring due to the deviation from technical regulations or inability to stick to them, which may be the consequence of either old equipment or sticking to generally accepted procedures of the execution, as well as requirements for a cheaper execution. The thesis presents the description of experiences gained during the execution works, the results of control examinations, the problems that occurred during the execution and appropriate solutions. In the phase of the jet-grouting-piles execution, which were used as a supporting structure, the attention was on the technology of the single fluid system and its effectiveness in the ground, while with ground anchors the most attention was paid to ground anchor installation and. The problems occurring on the construction site are often result of an incomplete project documentation, often involving the old and incomplete documentation of neighbouring buildings. The solution of issues in relation to the unexpected ground conditions, which significantly delayed the execution of works, is examined.

Keywords:graduation thesis, construction pit, jet grouting, modefied jet grouting (precuting), grout, temporary ground anchors