izpis_h1_title_alt

Konstrukcijski vidiki zamenjave visokotlačne turbine v jedrski elektrarni
ID Blatnik, Blaž (Author), ID Sekavčnik, Mihael (Mentor) More about this mentor... This link opens in a new window, ID Vukašinović, Nikola (Co-mentor)

.pdfPDF - Presentation file, Download (6,47 MB)
MD5: 8B77FDE012F30AE0DFC2181B630F7755

Abstract
V magistrskem delu smo obravnavali različne vidike zamenjave visokotlačne parne turbine v jedrski elektrarni. Glavni cilj naloge je bil raziskati logistične ukrepe v fazi priprave na menjavo visokotlačne turbine. V ta namen smo izdelali 3D model visokotlačne parne turbine, njenih parovodov, betonskega temelja in vseh štirih regulacijskih ventilov. Za izdelavo verodostojnega računalniškega modela smo izvedli 3D laserske meritve celotnega turbinskega dela postrojenja. Z uporabo 3D modela smo analizirali gradbeno konstrukcijo za prostorske omejitve pri načrtovanju zamenjave visokotlačne parne turbine. Izdelali smo 3D model dodatnih podpor parovodov. Določili lokacijo rezanja in varjenja parovodov. Z uporabo 3D modela smo tudi analizirali in predlagali postopke zamenjave visokotlačne parne turbine.

Language:Slovenian
Keywords:visokotlačna turbina, jedrska elektrarna, 3D laserski posnetek, parovodi, 3D modeliranje, betonski temelj
Work type:Master's thesis/paper
Typology:2.09 - Master's Thesis
Organization:FS - Faculty of Mechanical Engineering
Place of publishing:Ljubljana
Publisher:[B. Blatnik]
Year:2020
Number of pages:XXII, 63 str.
PID:20.500.12556/RUL-121806 This link opens in a new window
UDC:004.925.84:621.165(043.2)
COBISS.SI-ID:38610435 This link opens in a new window
Publication date in RUL:30.10.2020
Views:824
Downloads:129
Metadata:XML RDF-CHPDL DC-XML DC-RDF
:
Copy citation
Share:Bookmark and Share

Secondary language

Language:English
Title:Constructional aspects of high pressure turbine replacement in nuclear power plants
Abstract:
In the master's thesis, we discussed various aspects of replacing a high-pressure steam turbine in a nuclear power plant. The main goal of the task was to investigate the logistical measures in the preparation phase for the replacement of the high-pressure turbine. For this purpose, we created a 3D model of a high-pressure steam turbine, its steam pipelines, concrete foundation and all four control valves. To create a credible computer model, we performed a 3D laser scan of the entire turbine section of the plant. When planning the replacement of the high-pressure steam turbine, we analyzed the building structure for space constraints using the 3D model. We made a 3D model of additional steam pipeline supports. We also determined the location of cutting and welding of steam pipelines. Using the 3D model, we also analyzed and proposed procedures for replacing a high-pressure steam turbine.

Keywords:high-pressure turbine, nuclear power plant, 3D laser scan, steam pipelines, 3D modeling, concrete foundation