V podjetju, kjer se ukvarjajo z izdelavo ohišij za energetske transformatorje, se kljub povečanju proizvodnih kapacitet količina izdelkov ni bistveno povečala. Na oddelku sestave smo zato z orodji vitke proizvodnje in analizo toka vrednosti poskusili skrajšati pretočni čas izdelave podsklopa ohišja – stranice kotla. V prvem delu smo se seznanili s filozofijo vitke in metodami vitke proizvodnje, v drugem delu pa smo predstavili proizvodni proces izdelave transformatorskega ohišja. Proces izdelave stranice smo analizirali z metodo VSM. Izdelali smo diagram trenutnega stanja, ki smo ga z uporabo metod vitke proizvodnje in nekaterih tehnoloških rešitev izboljšali in izboljšan proces prikazali z diagramom idealnega stanja. Pretočni čas izdelave stranice smo skrajšali s 93,5 h na 21,33 h.

Jezik:Slovenski jezik
Ključne besede:vitka proizvodnja, analiza toka vrednosti, projektna proizvodnja, transformatorsko ohišje, varjena konstrukcija
Vrsta gradiva:Diplomsko delo/naloga
Tipologija:2.11 - Diplomsko delo
Organizacija:FS - Fakulteta za strojništvo
Kraj izida:Ljubljana
Založnik:[T. Župevc]
Leto izida:2019
Št. strani:XXII, 54 str.
PID:20.500.12556/RUL-107424 Povezava se odpre v novem oknu
UDK:005.935:658.5:621.314(043.2)
COBISS.SI-ID:16578587 Povezava se odpre v novem oknu
Datum objave v RUL:12.04.2019
Število ogledov:2196
Število prenosov:300
Metapodatki:XML DC-XML DC-RDF
:
ŽUPEVC, Tadej, 2019, Vitki proces izdelave ohišja energetskega transformatorja [na spletu]. Diplomsko delo. Ljubljana : T. Župevc. [Dostopano 28 marec 2025]. Pridobljeno s: https://repozitorij.uni-lj.si/IzpisGradiva.php?lang=slv&id=107424
Kopiraj citat
Objavi na:Bookmark and Share

Sekundarni jezik

Jezik:Angleški jezik
Naslov:Lean process of manufacturing a power transformer housing
Izvleček:
The company that produces power transformer housings recently enlarged their production capacities, however, the production output did not increase significantly. Therefore, we tried to shorten the lead time of transformer tank wall assembly using methods of lean manufacturing and value stream analysis. In the first part, we learned about lean philosophy and the lean manufacturing methods. The second part is the presentation of the transformer housing production process. The tank wall assembly process was analysed using the VSM method. We created a current state VSM diagram, which we improved using methods of lean manufacturing and some technological solutions. The improved process was presented using an ideal state VSM diagram. Lead time of side wall assembly process was shortened from 93,5 h to 21,33 h.

Ključne besede:lean manufacturing, value stream analysis, project manufacturing, power transformer housing, welding construction

Podobna dela

Podobna dela v RUL:
  1. lithium addition to aluminium cast alloys
  2. Mehanske lastnosti zlitine AlCu5,5Nd2,5
  3. Izdelava in predelava zlitine EN AW 6082 z dodatkom cirkonija
  4. Karakterizacija zlitine AlSi7Mg0,3
  5. influence of scrap revert type on mechanical properties of AlSi10Mg(Fe) alloy
Podobna dela v drugih slovenskih zbirkah:
  1. Preiskava zlitine AlZn10Si8Mg
  2. Quasicrystal-strengthened cast Al-alloys
  3. Influence of the working technology on the development of alloys H13-w(Cu) 87.5 %
  4. Vpliv parametrov pri kontinuirnem litju na mehanske lastnosti zlitine Cu-Cr-Zr
  5. Influence of compatibilizer concentration on mechanical properties of PP/PS blends

Nazaj