In master's thesis there is discussion about BIM progress monitoring of construction. The main discussion is about schedule and cost monitoring with Critical Path Method – CPM and Earned Value Management – EVM. The emphasis is on planning of business processes for construction monitoring with BIM, shown and explained on case study from actual infrastructure project. Business processes are shown with Integrated Definition of Function Modelling – IDEF0 and Business Process Modelling Notation – BPMN. Software used for monitoring is Bexel Manager and for graphical presentations Power BI. The thesis discusses further about construction monitoring, use of BIM for cost and schedule control and setting the right Key Performance Indicators – KPI’s for reaching project schedule and cost goals. Use of presented construction monitoring process in practice is explained with case study.
|